The JAB 6kW 14" replacement immersion heater is a single-element, 1¾" BSP heater for JAB DUC 2 unvented hot water cylinders. It is a straightforward like-for-like swap: drain down, unscrew the old element with a standard immersion spanner, fit the new one and reconnect. It suits a direct or indirect back-up heater position and keeps the hot water running when an original element has failed or scaled up.
At 6kW it delivers double the output of a standard 3kW element, so it recovers the cylinder faster on a dedicated, correctly rated electrical supply. Because the electrical load is high, the supply, cable and isolation must be sized for it, and the connection should be made by a competent person in line with BS 7671 and Part P.
Safety: isolate the electrical supply at the double-pole isolator and drain the cylinder before removing the old element. Never switch an immersion heater on until the cylinder is full of water, and make sure the element is fully submerged at all times. A 6kW load draws roughly 25A on a 240V single-phase supply, so the circuit, cable and isolator must be rated accordingly and the electrical connection must be made by a competent person.
Compatibility: the JAB DUC 2 Horizontal uses 3kW immersions as the standard fitment on every size from 125L to 300L. Before fitting a 6kW element, confirm with JAB that it is approved for your cylinder model, and check your supply can carry the extra load. Always match the 14" length and 1¾" BSP thread to the existing boss.
Good to know: replacing the element does not disturb the unvented safety kit, but the work is on a sealed pressurised system, so any other work on the cylinder must be carried out by a G3-qualified installer.
Key features
6kW high output
Double the heat input of a standard 3kW element for
faster recovery and quicker reheats.
1¾" BSP thread
The
standard sealed-system boss size used on JAB DUC 2 cylinders, not the larger 2¼" domestic boss.
14" element
The correct
immersed length to match the original heater position in the cylinder.
User-swappable
Unscrews with a
standard immersion spanner, with no special tools and no need to move the cylinder.
JAB DUC 2 spare
A
direct replacement for failed or scaled elements on JAB DUC 2 unvented cylinders.
Standalone or back-up
Heats the cylinder on its own, or provides
boiler or heat pump back-up on indirect models.
Specification
Heater
Application
Suitable for
JAB DUC 2 unvented hot water cylinders (confirm the model with JAB before fitting)
Use
Replacement for a failed or scaled element, standalone or back-up heating
Tool needed
Standard immersion spanner
Standards
Electrical
Wiring to BS 7671 and Part P
Unvented work
G3 (Building Regulations Part G3) for any work beyond the element swap
Frequently asked questions
Can I replace the immersion heater myself?
Mechanically, yes. It is a spanner-fit like-for-like swap: isolate the power, drain the cylinder, unscrew the old element and fit the new one with a good seal. The electrical connection should be made or checked by a competent person, particularly at 6kW.
What size and thread does it need?
This heater is 14 inches long with a 1¾ inch BSP thread. Check the boss on your cylinder before ordering. The common domestic 2¼ inch boss is a different size.
Will my supply handle 6kW?
A 6kW load draws roughly 25A on a 240V single-phase supply. It needs its own correctly rated circuit, cable and double-pole isolator. If you are unsure, have an electrician check the circuit before fitting.
Is a 6kW element approved for my JAB cylinder?
JAB lists 3kW immersions as standard on the DUC 2 Horizontal range. Confirm with JAB that a 6kW element is approved for your exact cylinder model and size before fitting.
Do I need to drain the cylinder first?
Yes. Isolate the electrics, shut off the cold supply and drain the cylinder below the heater position. Refill completely before switching the heater back on, as an element must never run dry.
Do I need a G3-qualified installer?
Not for the element swap alone, but any work on the unvented safety devices or pressurised system must be carried out and notified by a G3-qualified installer.